沒改考綱版:目前考試題型是200道單選題,四選一,考試時(shí)長為4小時(shí);
【濟(jì)南pmp考試題型是什么樣的?】新考綱版:待確認(rèn)
PMP考試題是雙語的,中英文對(duì)照,英文在上,中文在下,所以不用擔(dān)心語言問題 。
考試樣題:
While preparing the status report for stakeholders,the project manager discovers a negative
cost variance for a project where 10 percent of their work has been completed.What should the project manager do prior to meeting with the stakeholders?
A.Forecast the estimate at completion(EAC).
B.Initiate charge control procedures.
C.Put the project on hold until a response strategy is determined.
D.Use the contingency reserve.
1.在為相關(guān)方準(zhǔn)備狀態(tài)報(bào)告時(shí),項(xiàng)目經(jīng)理發(fā)現(xiàn)一成本偏差為負(fù)數(shù),該項(xiàng)目 10%的工作己經(jīng)完成,在與相關(guān)方開會(huì)之前,項(xiàng)目經(jīng)理應(yīng)該怎么做?
A.預(yù)測完工估算(EAC).
B.啟動(dòng)變更控制程序
C.擱置項(xiàng)目直到確定應(yīng)對(duì)策略
D.使用應(yīng)急儲(chǔ)備